Free Website Project Plan Template

A website project plan from discovery to launch — design, build, content and SEO.

Part of our free project plan templates.

Download Word (.docx)

Download PDF Free · No signup · No watermark

1.Project Overview

Project name {{Project name}}
Sponsor {{Sponsor / decision-maker}}
Project manager {{Project manager}}
Start date {{Start date}}
Target end date {{Target end date}}
Status {{Not started / On track / At risk}}

Keep this block on page one so anyone can see the project, its owner, and where it stands at a glance. Name one accountable project manager and one sponsor who can unblock decisions.

2.Objectives & Success Criteria

  • Launch {{the new website / redesign}} by {{date}} meeting {{measurable goals — e.g. faster load, higher conversion, mobile-friendly}}
  • Migrate content and preserve SEO (redirects in place, no ranking loss)
  • Hand over a CMS the team can update without a developer

Write objectives you can measure — “launch the new checkout by Q3 with under 1% error rate”, not “improve checkout”. If you cannot tell whether it is done, rewrite it.

3.Scope

In scope

  • Discovery, sitemap, and wireframes
  • Visual design and a responsive front-end build
  • CMS setup, content migration, and {{key pages / templates}}
  • SEO basics, analytics, redirects, and launch

Out of scope

  • {{Ongoing content marketing or SEO after launch}}
  • {{A separate web app, store, or portal}}
  • {{Brand / logo redesign, if not included}}

Naming what is out of scope is what actually prevents scope creep. Be explicit about the work people will assume is included but is not.

4.Milestones & Timeline

MilestoneOwnerTarget dateStatus
Discovery & sitemap approved{{PM}}{{Date}}{{Status}}
Design approved{{Designer}}{{Date}}{{Status}}
Build complete (templates & CMS){{Developer}}{{Date}}{{Status}}
Content loaded & reviewed{{Content lead}}{{Date}}{{Status}}
QA & cross-browser testing passed{{QA}}{{Date}}{{Status}}
Launch / go-live{{PM}}{{Date}}{{Status}}

Milestones are checkpoints, not tasks — a handful of dates that prove the project is moving. Each should be a clear “done / not done”, with one owner.

5.Tasks & Work Breakdown

TaskOwnerStartDueStatus
{{Run discovery and build the sitemap}}{{Owner}}{{Start}}{{Due}}{{Status}}
{{Design key page templates}}{{Owner}}{{Start}}{{Due}}{{Status}}
{{Build templates in the CMS}}{{Owner}}{{Start}}{{Due}}{{Status}}
{{Migrate content and set up redirects}}{{Owner}}{{Start}}{{Due}}{{Status}}
{{QA, fix, and launch}}{{Owner}}{{Start}}{{Due}}{{Status}}

Break the work into tasks small enough to track in a week or less. Give each an owner and a due date; a task with no owner will not happen.

6.Roles & Responsibilities

RoleNameResponsibility
Project manager{{Name}}Owns scope, schedule, and stakeholder sign-off
Designer{{Name}}Owns UX and visual design
Developer{{Name}}Builds the front end and the CMS
Content lead{{Name}}Writes/migrates content and manages SEO

Assign responsibilities to roles so the plan survives a team change. Be clear who decides, who does the work, and who needs to be kept informed.

7.Risks & Mitigation

RiskImpactLikelihoodMitigationOwner
{{Content arrives late and delays launch}}{{High}}{{High}}{{Lock a content deadline; start early}}{{Owner}}
{{SEO/traffic drop after migration}}{{High}}{{Med}}{{Full redirect map; keep URLs where possible}}{{Owner}}
{{Scope creep — extra pages/features}}{{Med}}{{High}}{{Change-request process}}{{Owner}}

List the few risks that would actually derail the project, rate impact and likelihood (High/Med/Low), and name the action and the owner. Review this table at every status check.

8.Budget

ItemEstimateActual
{{Cost item — labor, tools, materials}}{{Estimate}}{{Actual}}
Contingency{{Estimate}}{{Actual}}

Estimate the main cost lines and add a contingency for the unknowns. If your project has no budget, keep the section and write “N/A” — reviewers expect to see it.

9.Approval

Project Manager Name Signature Date
Sponsor Name Signature Date

Both sign-offs confirm the plan, scope, and budget are agreed before work starts.

A worked example for a B2B company’s marketing-website redesign.

1.Project Overview

Project name Northwind.com Redesign
Sponsor VP Marketing
Project manager Sara Ito (PM)
Start date July 1, 2026
Target end date October 15, 2026
Status On track

2.Objectives & Success Criteria

  • Launch the redesigned marketing site by Oct 15 with a 30% faster load and a clearer path to demo
  • Migrate all 80 pages and blog posts with redirects and no organic-traffic loss
  • Give Marketing a CMS they can edit without engineering

3.Scope

In scope

  • Discovery, new sitemap, and wireframes for key templates
  • Visual design and a responsive build on the new CMS
  • Migration of 80 pages and the blog, plus SEO and analytics setup
  • Redirect map, QA, and launch

Out of scope

  • The logged-in customer portal (separate project)
  • A logo or brand refresh (already done this year)
  • Ongoing content production after launch

4.Milestones & Timeline

MilestoneOwnerTarget dateStatus
Discovery & sitemap approvedSara ItoJul 18Done
Design approved (home + 5 templates)Designer (Mei)Aug 8In progress
Build complete on the CMSDev (Owen)Sep 12Not started
Content migrated & reviewedContent lead (Jo)Sep 26Not started
QA & cross-browser passedQA (Sam)Oct 8Not started
LaunchSara ItoOct 15Not started

5.Tasks & Work Breakdown

TaskOwnerStartDueStatus
Stakeholder interviews, analytics audit, and sitemapSara ItoJul 1Jul 18Done
Wireframes and visual design for the core templatesMei ChenJul 21Aug 8In progress
Build templates and components in the CMSOwen ReedAug 11Sep 12Not started
Migrate 80 pages + blog and build the redirect mapJo BanksSep 1Sep 26Not started
QA, accessibility and cross-browser fixes, then launchSam ParkSep 29Oct 15Not started

6.Roles & Responsibilities

RoleNameResponsibility
Project managerSara ItoOwns scope, schedule, and stakeholder sign-off
DesignerMei ChenOwns UX and the visual design system
DeveloperOwen ReedBuilds templates and the CMS, sets up redirects
Content leadJo BanksMigrates content and protects SEO

7.Risks & Mitigation

RiskImpactLikelihoodMitigationOwner
Content rewrite runs late and pushes launchHighHighLock a content-freeze date of Sep 19; start writing nowJo Banks
Organic traffic drops after migrationHighMedMap every redirect, keep URLs where possible, monitor GSC post-launchJo Banks
Stakeholders request extra pages mid-buildMedHighChange-request log; defer non-launch pages to phase 2Sara Ito

8.Budget

ItemEstimateActual
Design & development (agency + internal)$48,000
CMS license and hosting (year 1)$6,000
Contingency$5,000

9.Approval

Project Manager Name Signature Date
Sponsor Name Signature Date

How it works

  1. Preview the website project plan — objectives, scope, milestones, tasks, roles and risks.
  2. Download Word/PDF, or copy the text to paste into Google Docs or a sheet.
  3. Fill in your discovery, design, build and content milestones with owners, then share it for sign-off.

Frequently asked questions

What should a website project plan include?

A website project plan should set the launch goal and success metrics, the scope (design, build, content, CMS, SEO) and what is out, milestones from discovery and design approval through build, content, QA and launch, a task breakdown with owners and dates, the team roles, and the key risks. This template lays out those sections with a worked redesign example.

What are the phases of a website project?

Most website projects move through discovery and sitemap, wireframes and visual design, build (templates and CMS), content migration, QA and cross-browser testing, and launch. The template’s milestone table follows that sequence so you can put a date and an owner on each gate.

How do you avoid losing SEO when you redesign a website?

Keep URLs where you can, build a complete redirect map from every old URL to its new one, preserve titles and key content, and submit the new sitemap. Plan the redirects as a task in the plan and monitor Google Search Console after launch. The template flags SEO/traffic loss as a risk to mitigate.

How long does a website project take?

A simple marketing-site refresh can take 6–8 weeks; a full redesign with new design, a CMS, and content migration often runs three to four months. The biggest variable is content — it is the most common cause of delay, so the template treats a content deadline as a milestone and a risk.